Measure M Projects: Local Streets

Penngrove Area & Railroad Ave. Improvements

Reduce traffic congestion in and around the town of Penngrove. Provide access to Highway 101 at Railroad Avenue Interchange

Project Details:
The first phase of this project entailed updating traffic volumes and determining origin and destination of those vehicles traveling through community of Penngrove. The origin/destination (O/D) study report has been completed. Such information could be used to develop a cost sharing formula for surrounding “contributing” jurisdictions. The next step will be to conduct a traffic operational study. Operational improvements anticipated by the County Department of Transportation and Public Works (TPW) include signalizing the intersection of Old Redwood Highway North and Goodwin/Ely Road; realigning and signalizing the intersection of Old Redwood Highway North and Railroad Avenue; and, realigning and signalizing of the intersection of Old Redwood Highway North and Adobe Road.

Project Status / Schedule
The Origin/Destination Study has been completed. Traffic operational studies have not yet begun.

Measure M Programming Capacity
The County programmed $0.2 Million of the $19 Million identified in the Measure M Expenditure Plan for the origin/destination study ($18.8 Million remaining).

Project Sponsor:
County of Sonoma Department of Transportation and Public Works

Stakeholders:
Penngrove
Cotati
Rohnert Park
Santa Rosa
Petaluma

Total Measure M-LSP Other Need
$38,000 $200 $0 $37,800