3) Wilfred (Rohnert Park Expressway to Santa Rosa Avenue)

3) Wilfred (Rohnert Park Expressway to Santa Rosa Avenue)

This project added approximately 1.6 miles of HOV lanes in each direction. It also included auxiliary lanes between the Rohnert Park Expressway and Wilfred Avenue Interchanges, a southbound collector/distributor road between Santa Rosa Avenue and Wilfred Avenue, ramp improvements, an expansion of an existing park-and-ride lot, modifying the local street network (including a direct connection from Golf Course Drive to Wilfred Avenue) to improve access and circulation, and intelligent transportation systems, including ramp metering. The Wilfred project started construction in early 2009 and was completed in June 2013. A follow-up landscaping project is planned, but not yet funded.

The Caltrans website for this project is located at: http://www.dot.ca.gov/dist4/wilfredave/

The environmental document for the Wilfred project can be found at: http://www.dot.ca.gov/dist4/envdocs.htm#wilfred